1.
Housing Department closely monitors
contractor's performance
1. Housing Department closely monitors contractor's
performance
Hong Kong Government,
3 January 2006
The following is issued on behalf
of the Housing Authority:
The Housing Department would continue
to closely monitor and review the performance of the contractor
for three public housing construction sites, the Deputy Director
for Housing (Development and Construction), Ms Ada Fung, said today
(January 3).
The construction sites are construction
of Redevelopment of Shek Pai Wan Estate Phase 2; construction of
Fanling Area 36 Phase 1 and construction of Fanling Area 36 Phase
2.
Speaking in response to press enquiries
on a report in a Chinese newspaper today, Ms Fung said works progress
in the three contracts undertaken by the same contractor was slow.
"Having reviewed the situation,
the Building Committee and Tender Committee of the Housing Authority
have decided to give the contractor more time to see if the contractor
can comply with the requirements of the contract in a sustainable
manner," Ms Fung said.
She
stressed that this would not affect the total public housing production
commitment and the average waiting time. |