| News
Stories: |  |
Click-on these
handy "jump links" to quickly access the news item you're looking
for. 1.
LCQ18: Chek Lap Kok airport project 2.
Traffic arrangements facilitating KCR works implement
tomorrow 3.
Award of Airport Expansion Contract to Balfour Beatty
Group
1. LCQ18: Chek Lap Kok airport project Following
is a question by the Hon Emily Lau and a written reply by the Secretary for Economic
Services, Ms Sandra Lee, in the Legislative Council today (April 10): Question:
Regarding claims against the Airport Authority by contractors in relation to the
Chek Lap Kok airport project, will the Executive Authorities inform this Council
of: (a) the number of such claims that were settled in the past 24 months, the
nature of each claim and the total amount of compensation involved; (b) the comparison
between the amount of compensation as settled in each of such claims and the original
estimate of the contract from which the claim arises; and (c) the number of claims
still unresolved and the estimated contingent liability? Reply: Madam President,
During the past 24 months (i.e. April 2000 to March 2002), the Airport Authority
has settled a total of 6 779 claims relating to 30 airport related contracts.
Of the 6 779 claims, 3 745 arose from variations to works, for which the contractors
could make legitimate claims in accordance with the contract terms. This is a
commonly accepted practice, since such variations are normally envisaged in works
contracts. The other 3 034 claims fall into the following categories:
| | | No.
of claims | | (a) | work
site access, design / technical requirement issues | 1494 |
| (b) | design
and construction interface issues among contractors | 897 |
| (c) | other
miscellaneous items | 643 |
| e.g. adverse
ground conditions | |
| Total: | 3034 |
Some of the claims
above also involve minor additional works and the contractors could make claims
for these additional works under the contract. We have no detailed breakdown of
these items. The total amount of settlement for all the above-mentioned 6 779
claims was $3,795 million and the original estimates of the contracts from which
the claims arose was $22,612 million. As these claims involve sensitive commercial
information and in some cases, both parties are bound by a confidentiality clause,
the Airport Authority cannot reveal the amount settled for each claim. The Airport
Authority is still negotiating with contractors for settlement under four contracts
involving 10 claims. As the negotiations are ongoing, the Airport Authority considers
it undesirable to disclose the estimated contingent liability concerned. [Source:
Airport Authority Hong Kong, 8 April 2002] 2.
Traffic arrangements facilitating KCR works implement tomorrow
To facilitate the works of KCRC's Tsim Sha Tsui Extension, the following temporary
traffic arrangements will be implemented at Tsim Sha Tsui from 10 am tomorrow
(April 12) for a period of about nine months: * the section of Mody Road between
Nathan Road and Bristol Avenue will be temporarily closed to all vehicular traffic;
* the section of Carnarvon Road between Nathan Road and Humphreys Avenue will
be temporarily re-routed from one-way westbound to one-way eastbound; * vehicles
on Hanoi Road northbound will be prohibited from left turning onto Carnarvon Road;
* vehicles on Humphreys Avenue eastbound will be prohibited from right turning
onto Carnarvon Road; * vehicles on Hanoi Road northbound will be diverted via
Carnarvon Road eastbound; * vehicles on Carnarvon Road southbound north of Humphreys
Avenue will be diverted via Prat Avenue; and * vehicles on Humphreys Avenue eastbound
will be diverted via Carnavon Road northbound or Prat Avenue. Motorists are advised
to attend to the traffic signs erected on site. [Source:
Hong Kong Government, 11 April 2002] 3.
Award of Airport Expansion Contract to Balfour Beatty Group
Recent award to Balfour
Beatty of the HK$420m East Hall Works project at Hong Kong International Airport.
Airport Authority adopted a totally new and partnering focused procurement system
for this project, and intend to use similar systems for other complex projects
at the airport. After a pre-qualification exercise AA shortlisted three tenderers
to take part in a "pre-tender development phase" where the shortlisted
tenderers were based in AA offices, given full access to the design documentation,
allowed to interrogate and propose amendments to the Conditions of Contract, encouraged
to take part in VE workshops and to develop their base and alternative proposals
with the Authority and its designer. The three tenderers then submitted competitive
base tender bids plus alternative bids (using the data they had gleaned in the
pre-tender development phase). After a technical and financial assessment the
project was awarded to Balfour Beatty. All pre-tender development work was undertaken
confidentially and the two unsuccessful shortlisted tenderers were reimbursed
a portion of their costs incurred during the process. The two unsuccessful shortlisted
tenderers were Gammon Skanska and Hsin Chong Taylor Woodrow JV. The objective
of this approach was to give the tenderers a complete understanding of the complexity
of this project and the operational constraints before they submitted a price.
We wanted to ensure that the winning Contractor fully understood what they were
letting themselves in for and that they priced their tender accordingly. We have
had some very positive feedback from the Contractors involved in this process.
If you
would like any more information please call: David Brodie-Stedman,
Procurement Manager, Tel: 2769 1234, Airport Authority Hong Kong. [Source:
Airport Authority Hong Kong, 8 April 2002] |