| News
Stories: |
 |
Click-on
these handy "jump links" to quickly access the news item you're
looking for.
1.
Urban renewal chief lays out plans
2.
'Why must everything look like a wet
market?'
3.
Design and build drive for road contracts
4.
Savings built with alliances
5.
MTRC renews $6b funds call for new
lines
6.
300,000 a day expected to use new MTR
Island lines
1. Urban renewal chief lays out plans
CHLOE
LAI, SCMP 25 May 2004
Reviving
slum areas to improve the environment and attract investment will
be the Urban Renewal Authority's goal in the next three years, new
chairman Edward Cheng Wai-sun said yesterday.
Mr
Cheng, who took up the post three weeks ago, cited the redevelopment
of Russell Street in Causeway Bay as an illustration of his approach
to urban renewal.
"Russell
Street used to be very rundown, but now it is a very lively, busy
street full of shops and people. The spillover from Times Square
has revitalised the street," he said.
He
said the authority would use a similar approach to ageing districts,
such as Mongkok, Kwun Tong and Wan Chai.
"The
most important thing is confidence. If we can demonstrate to the
public and the business community that this model works, we will
have their support and investment," he said.
"The
authority has limited resources. It does not have enough to revitalise
all the rundown areas. But it is enough for us to kick-start [the
process].
"So
we have to be more focused and let the spillover effect of those
redeveloped districts bring life and investment into the ageing
neighbourhood."
But
Mr Cheng said the authority had a social responsibility to redevelop
urban slums with little commercial value, such as Shamshuipo.
"It
is our social responsibility to improve the environment of those
who live there," he said.
The
authority was set up three years ago to implement 225 redevelopment
projects over 20 years.
The
authority is also responsible for rehabilitating old but serviceable
buildings, preserving historic structures and revitalising old neighbourhoods.
2. 'Why must everything look like a wet market?'
JOSEPH
LO, SCMP 25 May 2004

An artist's impression of the proposed new bus terminal in Tsim
Sha Tsui East, which the Tourism Board's Selina Chow described as
"terrible".
Redeveloping
the Tsim Sha Tsui harbour promenade risks destroying one of Hong
Kong's top stops for visitors, Tourism Board chairwoman Selina Chow
Liang Shuk-yee warned yesterday, after she and fellow legislators
were given detailed proposals.
"Looking
at the artists' impressions, it looks like a wet market. Why does
everything we do look like a wet market?" she said.
"In
the past, we have always said, `okay, the government's building
it, so it's going to be less than beautiful'. But if the point is
to beautify Tsim Sha Tsui, then we must do better."
The
Economic Development and Labour Bureau presented draft proposals
for the $242 million redevelopment, under which the bus terminal
adjoining the Star Ferry pier would be moved to Tsim Sha Tsui East
and the site turned into a plaza, with footbridges and a podium
garden connecting the pier and the new terminal adjoining the Wing
On Plaza Garden.
The
Star Ferry taxi stand would be moved to Canton Road and parking
bays for tour coaches and shuttle buses moved beyond the proposed
plaza to an area outside the Hong Kong Cultural Centre. New bus
stops would be put in at the bottom of Canton Road and a high-frequency
shuttle bus would run to and from the new bus terminus.
Tourism
Bureau staff, led by Permanent Secretary for Economic Development
Sandra Lee Suk-yee, told the Legislative Council's economic services
panel the redevelopment would improve pedestrian circulation and
enhance Tsim Sha Tsui as a popular and prominent tourist district.
But
Mrs Chow said the government's design was terrible and risked damaging
tourism by "uglifying" one of the city's most important
tourist spots. The government hopes that construction of the plaza
and the pedestrian links will begin in September, for completion
in April 2006.
Mrs
Chow said the government should have learned its lesson from the
design of the Cultural Centre, which she said had been criticised
in the past as having no significant architectural qualities.
"[The
design of the Cultural Centre] is not timeless, it's not beautiful.
But no lessons seem to have been learned," she said.
The
legislator also criticised the lack of escalators on the proposed
footbridge linking the promenade with the new bus terminal.
"Even
wet markets have escalators nowadays," Mrs Chow said.
Democratic
Party legislator Sin Chung-kai said his party supported the redevelopment
but agreed with other legislators that more design work needed to
be done before the project went ahead.
The
legislator representing the transport sector, Miriam Lau Kin-yee,
voiced concern that transport interest groups had not been properly
consulted.
"Has
government consulted the taxi trade? I'm concerned about whether
the taxis will protest over having their stand moved" to Canton
Road, Ms Lau said.
3. Design and build drive for road contracts
Keith
Wallis, The Standard 25 May 2004
The
Highways Department is overhauling the way it procures construction
projects with a stronger focus on design and build and public-private
partnership deals, according to Director of Highways Mak Chai-kwong.
Speaking
at a seminar on Friday organised by the Lighthouse Club construction
charity, he said the department has just awarded a pilot public-private
partnership road maintenance contract covering high-speed roads
in the north-west New Territories.
He
said the department would review the progress of the contract at
the end of this year with a view to extending the concept to other
road maintenance projects.
According
to Mak, the department usually spends about HK$800 million a year
on its road maintenance programme, which is split between 12 contracts.
Now,
he wants to combine and lengthen the contracts and envisages seven
to eight deals lasting five to eight years.
Aside
from offering better value for money, Mak said, ``more importantly
it would establish a new culture'' where contractors would be expected
to use their own staff and equipment rather than use multiple layers
of subcontractors.
``We're
adopting more design and build contracts'', which enables contractors
to have early involvement in a project, making it easier to tackle
problems and find solutions.
Mak
said a feasibility study by Beijing's Highway Planning and Design
Institute into plans for the Hong Kong-Macau-Zhuhai bridge would
be completed by the end of this year or early in the next. The plan
awaits State Council's approval.
He
said the Highways Department had set up at project management office
to oversee Hong Kong's contribution to the project.
Turning
to the Central-Wan Chai bypass, part of the controversial Central
and Wan Chai reclamation projects, Mak was confident the highway
would be implemented.
``We're
thinking of doing it in two stages,'' he said.
On
a general note, Mak said the department has drafted several measures
to reduce conflict in construction.
These
include post-contract partnering, now a norm on all major projects,
and identifying problems early on in the construction process.
Mak
said that overall the department is the ``big spender'' among government
departments with HK$45 billion earmarked for projects between 2003
and 2008, or an average of HK$9 billion a year.
4. Savings built with alliances
Danny
Chung and Keith Wallis
Hong
Kong's construction industry is realising there is a better way
to building and completing projects than the traditional adversarial
relationship between client, contractor, professional team and subcontractors.
As
more than 100 construction specialists heard last Friday the shift
towards a more collaborative way of working is not always easy,
but it is producing positive results on both road and rail projects.
The
group, including representatives from contractors, consultants,
clients, insurers, lawyers and academia, attended a seminar organised
by the Lighthouse Club construction charity.
Outlining
the changes being made by the MTR Corp, probably Hong Kong's most
enlightened client, Kumagai Gumi deputy regional general manager
Russell Jones said savings of between HK$5 million-HK$10 million
had been achieved on a project in Tsim Sha Tsui.
The
HK$300 million scheme involves modifications to Tsim Sha Tsui station
to help connect with pedestrian subway links being built by the
Kowloon Canton Railway Corporation as part of its East Rail extensions.
MTR
Corp procurement and contracts manager Martin Dunn said the extensive
project requirements coupled with the tight construction deadline
meant both MTR Corp and Kumagai Gumi agreed ``that innovation and
initiative were going to play an important roll''.
He
added: ``The objective required the best overall solution, not the
optimum for Kumagai or MTR, but the best overall solution taking
due cognisance of time, quality, safety, budget and environment,
all of which pulled as counter forces to each other''.
The
balance was achieved by ``engineering out all unnecessary costs
while issues such as maintainability, life-cycle costing, constructability,
logistics of ordering, installation and delivery were all factors
that needed consideration''.
Dunn
pointed out that the project was awarded as a target cost contract,
so that any savings were shared equally between MTR Corp and Kumagai
Gumi or with Kumagai Gumi and its electrical and mechanical (E&M)
contractor, Balfour Beatty. Equally any overruns were split the
same way.
Dunn
said Kumagai Gumi ``was paid a not unsubstantial sum ... in line
with the target obligation for August last year'' and a further
payout ``again quite substantial'' is forecast for this August.
There
were also savings on the E&M works, which have so far generated
HK$1.1 million in cost reductions, equivalent to 2.23 per cent of
the contract value. Work is also up to six weeks ahead of programme.
Jones
said that overall there are expected to be total savings of HK$15
million on the whole project which is expected to be completed six
weeks early.
``We
have achieved a 5 per cent saving on cost on one of the most technically
demanding jobs in Hong Kong.''
A
similar enlightened approach is being taken by Spanish main contractor
Necso Entrecanales Cubiertas and subcontract partner VSL on the
construction of the Lai Chi Kok viaduct, part of the Route 8 highway
between Tsing Yi and Sha Tin.
Necso
general manager Robert Park said the alliancing approach taken by
the firms was more of an ``enlightened partnership of equals. The
impetus for this - is that that there must be a better way of working
- anything cannot be worse than the traditional approach. Alliancing
in various forms has been around for some time and is in effect
- partnering in its ultimate form''.
He
said alliancing was ``basically about people working together for
a shared objective. You remove all the confrontational aspects from
a traditional subcontract''.
Outlining
the preparations before the alliance was agreed, Park said the main
contractor and subcontractor defined the scope of work that would
be undertaken to an agreed target cost estimate.
Staff
from the main contractor and subcontractor plus an outside expert
formed the alliance team that was based in a single project office
instead of the traditional approach of individual firms using separate
site cabins.
``The
alliance agreement is a fairly simple document - easily understood
and is not like a normal contract,'' Park said.
Cost
savings are shared between Necso and VSL with a portion going to
the alliance team. Any increase is shared between the Necso and
VSL.
A
key feature of the arrangement was the open book set up where ``all
correspondence is shared'' throughout the life of the project. ``Everything
is entirely open,'' Park said.
``VSL
members of the alliance have the same rights of access to the correspondence
databases, as do Necso members,'' VSL Intrafor Asia Pacific chief
executive Andrew Payne said.
Common
office services and support would also be shared. Other benefits
included reduced correspondence, the establishment of a long term
relationship and common interests, Park said.
James
Blake, former Kowloon-Canton Railway Corporation senior direct capital
works and now a consultant for the rail company, said: ``I don't
see why an alliancing approach with the [public] employer should
not be feasible in Hong Kong.''
5. MTRC renews $6b funds call for new lines
Staff
reporter, The Standard 25 May 2004
The
MTR Corporation has warned again that its proposed HK$15 billion
West and South Island lines will be scrapped if the government refuses
to fund about half the cost.
It
says the financing can take the form of an cash injection of nearly
HK$6 billion, coupled with the MTR being granted property development
rights at Wong Chuk Hang station, with an estimated sales revenue
of almost HK$1.5 billion.
MTR
also said fare revenue of the new lines will range from HK$3.80
per passenger per trip to HK$6.80, far below HK$9.90 to HK$14.40
estimated by its rivals. It says the revenue will not be enough
to finance the scheme, so it needs government assistance to cover
the shortfall.
MTRC
project director Russell Black told a media briefing that if the
government decides not to provide financial support, the MTRC will
have no alternative but to drop the project.
Property
development rights on a five hectare site at Wong Chuk Hang terminus
will comprise a residential and retail complex. The estimated property
sales income represents almost 20 per cent of the total funding
of HK$7.5 billion.
An
Environment, Transport and Works department spokesman said the government
has yet to decide on financing the new lines project, which is under
study.
According
to a feasibility study, the lines have a total length of about 7.5
kilometres. MTRC plans to run four-car units, which will be cheaper
to operate than the high-capacity heavy units it uses on its existing
network.
The
Legislative Council's transport panel will discuss the rail links
together with the Route 7 highway project on Friday after the government
received the MTRC document last month.
Plans
call for the extension of the Island Line from Sheung Wan to Sai
Ying Pun, where it will connect with the West Island Line that will
run in a tunnel around the western edge of Hong Kong Island to Wong
Chuk Hang. New stations will be built at Sai Ying Pun, Wong Chuk
Hang, University, Kennedy Town, Cyperport, Wah Fu and
Aberdeen. The MTR Corp is considering the possibility of building
a station at Queen Mary hospital, although it expects less patronage.
The
South Island Line will run from South Horizons to Admiralty and
include stations at Lei Tung, Wong Chuk Hang, where an interchange
will be built to link with the West Island Line and the Ocean Park.
The
MTRC has put forward three route options between Ocean Park and
Admiralty - a direct link, a route via Happy Valley, or via Happy
Valley and Wan Chai.
Route
7, a highway alternative to the rail line, is hotly opposed by environmentalists.
6. 300,000 a day expected to use new MTR Island lines
JOSEPH
LO, SCMP 25 May 2004
The
MTRC expects about 300,000 passengers a day to use its new West
Island and South Island lines, which it hopes to complete by 2010.
The
Mass Transit Railway Corporation also said yesterday that it wanted
to build flats in Wong Chuk Hang to help cover some of the construction
costs for the projects.
Malcolm
Gibson, MTR chief design manager, said about one-third of the two
lines' passengers were expected to be cross-harbour commuters.
"About
400,000 people live in that area ... we expect them to take about
780,000 public transport journeys each day.
"Of
that figure, we expect to get about 300,000 [journeys]," Mr
Gibson said.
The
two lines would form a loop, with the West Island line running between
Sheung Wan through the Cyberport to Wong Chuk Hang, and the South
Island line running from Admiralty through Wan Chai, Happy Valley
or both to South Horizons. The two lines would connect at Wong Chuk
Hang.
Project
director Russell Black said the corporation had proposed to the
government that the expected $15 billion construction and financing
costs be partly subsidised by a housing development on top of a
train depot at Wong Chuk Hang.
|