| News
Stories: |
 |
Click-on
these handy "jump links" to quickly access the news item you're
looking for.
1.
Mulan ensures building of new spur
line is on track
2.
Engineering ways to value management
1. Mulan ensures building of new spur line is on track
Keith
Wallis, The Standard 31 August 2004
Mulan,
a massive tunnel boring machine (TBM) named after a fabled female
Chinese warrior, will start work next month on the second of two
tunnels being built as part of the Sheung Shui to Lok Ma Chau railway.
The
massive machine completed the excavation of the first tunnel three
weeks early in June.
The
tunnels are part of a HK$2.8 billion contract awarded to French
contractor, Dragages (HK) joint venture, by the Kowloon-Canton Railway
Corporation (KCRC) for the construction of the spur line's 5.2-kilometre-
long Sheung Shui-Chau Tau section.
Phillippe
Bouquet, Dragages (HK) joint venture project director, said the
aim was to complete both tunnel drives by October next year ready
for the installation of trackwork, along with power, communication,
ventilation and fire protection equipment.
Bouquet
said there hads been steady rather than spectacular progress, but
he was obviously pleased the first complete tunnel drive had finished
early.
As
a result, construction of the spur line is on course to be completed
and the link open to passenger traffic by mid-2007, providing a
more convenient entry point for people visiting western Shenzhen
from Hong Kong.
Mulan,
which was used to construct the Kwai Tsing tunnels on West Rail,
broke through on the second of two drives on June 21.
The
1,480-metre-long tunnel forms the western section from Chau Tau
to Kwu Tung station.
The
eastern approach - a 1,720-metre-long tunnel from Sheung Shui to
Kwu Tung station - was driven through last February.
Following
completion of the Chau Tau-Kwu Tong section, the main section of
the TBM, including its large-diameter cutterhead was dismantled,
transported to Sheung Shui and reassembled ready to start excavating
the Sheung Shui to Chau Tau line tunnel.
About
800 people will be working on site during the peak of construction.
Bouquet said Mulan was refurbished before it started tunnelling
work at Sheung Shui.
A
new cutterhead was shipped from Shanghai, while a new main drive
was sourced from the original TBM manufacturer in France.
An
extensive amount of noise protection was fitted to enable the machine
to comply with tough regulations that limit the amount of noise
to just 45 decibels.
Aside
from the tunnels, which also include small sections built using
cut-and-cover techniques, Dragages has two other main responsibilities
- connecting the spur line to the East Rail line north of Sheung
Shui station and the formation of advance works for Kwu Tung station.
He
said linking the two railways would be particularly tricky.
This
is because part of the existing East Rail line will be diverted
on to new track that has been sandwiched between the existing live
railway and the main pipelines carrying water from China.
Consequently
there was a considerable amount of discussion between KCRC, the
Water Supplies Department and other organisations even before construction
began to ensure there was little chance of disruption to train services
and disturbance to nearby residents.
With
a train running past the site every two minutes, there was extensive
monitoring of any ground settlement.
That
included installation of a sophisticated warning system during the
works to ensure there was no impact on train operations.
``The
target is to give back the site to KCRC early February next year,''
Bouquet said.
This
will allow KCRC to install trackwork and other systems prior to
connecting the spur line with the main line.
By
comparison, construction of much of the other civil engineering
work has been straightforward.
2. Engineering ways to value management
Danny
Chung, The Standard 31 August 2004
The
government, developers and large contractors have been making increasing
use of value management and engineering to slash unnecessary costs
and improve value.
Value
management was used on 18 projects over the past 18 months, Environment,
Transport and Works Bureau spokeswoman Josephine Wong said. A further
seven projects will have value management applied by next March.
The
greater use of value management was urged in the Construct for Excellence
report, published in January 2001 by the Construction Industry Review
Committee, a government-sponsored group headed by Henry Tang, now
financial secretary, that was appointed to look at ways of reforming
the industry.
Value
management and engineering is a system to develop and compare alternatives
to get the job done with the greatest efficiency, economy and quality
with the least delay. Workshops bring designers, contractors, subcontractors
and clients together over several days to consider more efficient
designs or ways of working on projects.
Despite
the growing use of value management in engineering, there is still
some way to go before it is widely accepted, City University building
and construction department lecturer Dr Leung Mei-yung said. ``Many
construction professionals do not know [about value management],''
she said, while those that may have heard of it may not understand
what it entails.
This
view was shared by Hong Kong Institute of Value Management chairman
Tony Wilson, who said: ``People know what value management is in
very general terms. They know it's a good thing, but they don't
really know the details.''
The
Hong Kong Institute of Surveyors and City University jointly run
training workshops on value management that are funded under the
professional services development assistance scheme.
Workshop
literature indicates that cost savings of 10 to 15 per cent can
be achieved on most projects.
|